Wooden trim around all units now completed and the base for the wet pour was done today.
The safety rails have been put in place but still need to be cemented in.
As you can see we now have swings, and they look fantastic. I was rather tempted to test them out, but refrained ;o)
Fence posts/panels put back, and in their new position.
The new posts cost £70.
More info on fence panels to follow.
Great idea from Alistair regarding Open Day.
Thought is to do a joint venture with Tennis Club to celebrate both Play Area & Pavilion. Possibly have a BBQ and a village game of rounders.
I've done a poster and will sent via email later. If we all agree to this I'll then inform NHDC/WREN the plan for the day.
Playdale now hope to finish Friday, and once papers signed, it will be all ours, ref insurance.
It will not however be open to the public until NHDC inspection done, so signage will be placed until then. Kids I'm sure will still venture in mind !!!
The rest of WREN paperwork to be done shortly and will also claim the remaining £500 grant money.